Electrical Protections of 33 kV Substation – ESSO Campana Fuel Refinery

Client: ESSO PETROLERA ARGENTINA S.R.L.


The incorporation of a new medium voltage cell in 33 kV Substation of the Refinery, to supply the Air Liquide Plant, required enlargement and testing of the existing differential busbar system, as well as the parameterization and testing of protections of new cell and others belonging to the incoming 33 kV feeders of the Refinery, like as feeder differential protection, overcurrents and directional overcurrents.




Generator Protection – Celulosa Argentina Capitán Bermúdez Pulp Paper Plant

Client: CELULOSA ARGENTINA S.A.


During the annual stop of the plant were carried out comprehensive testing corresponding to preventive maintenance of the ABB REG 216 generator protection, installed in the power plant.

The works included the detection and repair of fault presented in the protection, and subsequent testing of all functions built in the system.

Moreover complete testing of field devices, all analog circuits, signaling and tripping associated to generator protection were carried out.




Electrical Protections - Chabas 132 kV Substation

Client: AREVA S.A.


Configuration, setting and testing of AREVA transformer differential and overcurrent protections. Work was carried out during commissioning of 132 kV Chabas Substation.




Protection, Control and Measurement Devices - Molinos San Lorenzo Plant

Client: MOLINOS RIO DE LA PLATA S.A.


During the annual stop the plant were carried out electrical testing of Protection, Control and Measurement ABB REF 541 terminals, corresponding to the 33 kV cells of 33 kV in substations SET1, 7, 8, 10 and 12. Testing of all protection functions in service, included in each one of the terminals, were carried out trough secondary injection with the aid of three phase injection test set. Moreover functional testing of the cells was also carried out.




500 kV Current Transformers - Cobos 500 kV Substation

Client: AREVA S.A.


During the start-up of the new Cobos 500 kV Substation, 500 kV current transformers electrical testing have been conducted.

Followings testing were made:
– Ratio.
– Polarity.
– Excitation curve.
– Winding Resistance.
- Insulation resistance of secondary windings against earth.




355 MVA Combined Cycle TR10, TR11 and TR12 Transformers – Central Puerto Steam Power Plant

Client: ELECTROINGENIERÍA S.A.


Technical problems and repeated failures in the original Transformers of 786 MW Central Puerto Combined Cycle required the replacement of the faulty ones by new units. The project consisted in the protection calculation settings of the three new power transformers, and field services of setting and protections testing.

Parallax bottom

22 years of experience

on the Business.


Copyright © 2018 Kwell
en_USEN